SENIOR CENTER BUILDING SUB-COMMITTEE
Meeting #31, December 15, 2005
Homer Building Conference Room 2:00 PM
Present: Karen Pressey, Neil Hegarty, Walter Guertin, Pat Brusch, and Mary Ann Johnson
The sub-committee met to review the 6 proposals received for the Project Manager position.
The firms were:
Carlisle Consulting, Inc
John Ciccariello & Assoc.
Kellar Associates
Lincoln Consultants
Diversified Project Management Inc.
Company #6
Each member present read and reviewed each submittal. They then ranked the proposals as follows:
Carlisle Consulting, Inc
Lincoln Consultants
John Ciccariello & Assoc.
Karen will contact each firm and set up appointments for interviews on December 19, 2005 at the Senior Center starting at 5:00 PM.
Respectfully submitted,
Karen Pressey
Karen Pressey, Chairman
Senior Center Building Committee
|